Coors Field

DETAILS

Categories

Location

Services Provided

Construction Materials Testing, Environmental Services

DESCRIPTION

  • In 1992, K+A joined the team of ATEC/Kumar to provide quality control and soils and materials testing at Coors Field.  The project included:
    • Placing 63,000 cubic yards of concrete,
    • Performing 2,300 temperature, slump, air, and unit weight tests,
    • Testing 9,200 concrete specimens,
    • Excavating 181,000 cubic yards,
    • Testing 86,000 cubic yards of fill for classification, moisture, and density, and backfilling.
  • K+A also performed a dewatering study for a 70-foot by 82-foot storm water vault that collects and stores between 95 and 190 gpm of storm water runoff from the playing field.
  • The study addressed the installation of well points and sheet piling prior to excavating approximately 30 feet, about 5 feet below the existing ground water level.

Additional PROJECTS

Construction Materials Testing

Denargo Market Redevelopment

Construction Materials Testing

Platte Park by Windsor

Chatfield Reservoir Reallocation Construction Materials Testing

Chatfield Reservoir Reallocation

Construction Materials Testing

Regional Transportation District – Oversight Verification Testing and Quality Assurance

Waterton/Wadsworth Intersections Improvements Construction Materials Testing

Waterton/Wadsworth Intersection Improvements

Construction Materials Testing

Levitt Pavilion